Fermeture du tunnel jusqu'au 31 août
Fermeture complète du tunnel Léopold II 24 heures sur 24 et 7 jours sur 7. Cette fermeture est possible grâce à la réduction significative de la circulation automobile à Bruxelles. Afin de doser le trafic, une voie de circulation sera fermée dans...

Renovation work on the Leopold II tunnel

Status: 
En exécution

What is the aim of the work on the Leopold II tunnel? Renovation work takes place for various reasons but, in this case, the priority is improving safety. Of course, the necessary measures are taken to continuously ensure the safety of road-users, however it is now time to carry out serious renovation work to the Leopold II tunnel.

The work involves: asbestos removal, structural repairs, a new ventilation system, improved smoke removal capacity, new video monitoring, alarm system and fire detection, new technical spaces, etc. These works will ensure the Leopold II-tunnel becomes a shining example of safety and effective traffic flows and management.

 

General project information

Cities

  • Brussels city
  • Molenbeek-Saint-Jean
  • Koekelberg
  • Ganshoren

Contracting authorities

Bruxelles Mobilité

Rue du Progrès 80/1 
1035 Bruxelles
0800 94 001

Routes

Name Date More informations
Demande de permis d'urbanisme 1/12/2016
Obtention du permis d'urbanisme 13/7/2017 vergunning_leopold_ii.pdf
Réunions d'info pour les rivérains avril 2018 2018-04-23_renovation_leopold_ii-presentation_riverains_def_aangepast.pdf